The buildings, power and cooling behind AI, now measured in gigawatts.

Also called: data center, datacenter, gigawatt, GW, stargate, power grid, nuclear power, energy demand, ai factory, ai factories. In the glossary.

Datacenters & Energy is cooling this week (×0.5 against the eight weeks before). What is moving.

How it works, as a machineThe Campus Build Site · sites

Follow one site from a bare parcel and a power request to a hall that is switched on, in a datacenter campus build site with its substation yard.

  1. Answer the neighbors
  2. File the load request
  3. Batch the grid studies
  4. Set the transformer
  5. Fill the cooling loop
  6. Switch the hall on
Play Datacenters & Energy

Datacenters & Energy in plain words

A datacenter is the building that houses the chips AI runs on, together with the power lines and cooling that keep them working. The largest are now sized by the gigawatts of electricity they draw. Building one means securing power and cooling first, which has made energy part of the AI race.

An analogy

A commercial kitchen where the stoves are the easy part. Every burner needs gas piped in and every hood needs heat pulled out, so the kitchen grows only as fast as the gas main and the vents. Buy a hundred more stoves than the pipe can feed and they sit cold.

How Datacenters & Energy connects

5 typed relations in the knowledge graph

Builds on

  • GPUs & AI Chips: The racks a switched-on hall holds are the packaged chips built in the chip supply.

Built on by

  • Compute Buildout: The hall that is paid for about two years ahead is the site that datacenters follows from land to switch-on.
  • Funding & Valuations: The cluster being prepaid is built in a hall that needs power, land and a lead time of its own.

Made possible by

Limits

Often in the same sources

Compute Buildout, AI Revenue & Adoption, GPUs & AI Chips, AI & Jobs, Funding & Valuations, Open-Weight Models

See Datacenters & Energy in the knowledge graph

Who is behind Datacenters & Energy

people, labs, products and models

People

  • Elon Musk (built): SpaceXSI owns the Colossus GPU clusters and rents them out, including to Anthropic.

Named in its facts

What the sources say

3 parts · 9 sources · updated 2026-11-27

Sources describe a datacenter site as land and a power request that wait on the grid: the request is filed and studied for years, the transformers and turbines are sold out for years, and the hall is cooled and built for racks of hundreds of kilowatts. A finished hall can still sit dark until the grid says yes. Developers can bring their own power on site to bridge, at a higher cost, or wait for the utility; whether a campus helps the town it lands in is argued.

The land and the grid

A site begins as land and a request to the utility for megawatts. The request is studied against what breaks if the load is added, and in a stretched grid that line is long.

  1. The zoning counter answers the town: who the buyer is, noise, water and an air permit that fits how the site runs.
  2. The load request desk files the site's megawatts with the utility, with a study fee and a deposit per megawatt.
  3. The grid study queue tests what breaks if the load is added; a full connection can take 5 to 10 years.
5 to 10 years
Time to fully connect a large data center to the grid in Texas, as the essay author reports Ryan McEntush
474 GW
Large new customers in the Texas grid operator's queue by June, about 90% of it data centers, as the essay author reports Ryan McEntush
about five years
Average wait of a project in the US interconnection queue, as a16z writers report Matt Cronin
$100,000 + $50,000 per MW
Study fee and deposit under Texas large-load rules effective October 8, as the essay author reports Ryan McEntush
  • For about a decade a buyer found a utility with spare network capacity, signed up as a large load and contracted power to match its use on paper, often without proving the power could reach it. Ryan McEntush
  • That is over: the grid is stretched thin and almost any new large load or generator now needs an upgrade, and buying from one plant does not reserve a route to your building. Ryan McEntush
  • Developers spam requests across several sites and many are speculative builds with no customer yet, so planners cannot tell which are real and do not want ratepayers paying for upgrades for projects that never show up. Ryan McEntush

When it breaksHalls finished, switch-on paused. Texas' grid operator paused approvals for data centers of 75 MW or more to switch on, including 17 that had finished every other step. Until an audit settles which projects are eligible, the timeline is unknown and the load forecast is on hold. Ryan McEntush

Open questionDoes a data center campus help the town it lands in, or load it?

  • Counties that already run data centers show more housing, higher home values, less unemployment and more job growth since 2024. Moses Sternstein
  • More data centers are needed, but not next to homes: a 24/7 turbine whine from a campus beside houses is a zoning and permitting failure. AINews

The yard

Power equipment is the other long wait: transformers and turbines are sold out for years. Developers who cannot wait run their own power on site as a bridge, with the costs and limits of an island.

  1. The transformer bay takes a large power transformer, which now takes more than two years to arrive.
  2. The gas engine bay runs the hall on its own power until the grid connection comes, at a higher cost.
more than two years
Delivery time of large power transformers, as the essay author reports Ryan McEntush
five years
Wait for a new power turbine from a major maker, as a turbine startup founder describes it (reported, one speaker) Y Combinator
99% uptime, about 88 hours down a year
Uptime some on-site island designs aim for, as the essay author reports Ryan McEntush
30 minutes
Time within which a grid-adjacent campus must cut its use or switch to backup power when the grid operator calls, set by the Texas utility commission Ryan McEntush
  • Idle GPUs cost far more than the electricity to run them, so developers plan to bring power on site behind the meter, almost always alongside a grid connection or as a bridge to one. Ryan McEntush
  • Every site the essay author knows of intends to connect to the grid as soon as it can, chiefly because on-site power almost always costs more; once the grid is there, say in year five, you switch. Ryan McEntush
  • An island lacks what the grid supplies: when one plant trips, the other generating units cover for it, and the grid also provides inertia, fault current, steady voltage and black start. Ryan McEntush

When it breaksThe bridge turbines that whined at night. A Virginia data center ran on-site natural-gas turbines whose high-pitched whine never stopped, day and night; neighbors put mattresses and plexiglass in their windows. Commenters called siting it beside homes a zoning and permitting failure. AINews

Open questionWait for the utility, or bring your own power?

  • Stay utility connected, give the utility many years of notice and co-plan, for flexibility on both sides. Sequoia
  • Time to power matters most, so bring your own power on site, usually alongside a grid connection or as a bridge to one. Ryan McEntush

The hall

The hall is built around its racks: concrete, electrical and mechanical yards and cooling, with racks of hundreds of kilowatts on liquid loops. Switching it on is a grid event, so it must ride through faults and can be asked to cut back.

  1. The cooling pump fills the liquid loop that carries heat away from racks of hundreds of kilowatts.
  2. The switchgear board switches the hall on and rides through faults so the load does not drop off at once.
hundreds of kilowatts
Power of one AI rack today, against 10 to 40 kilowatts for a storage rack, as a Google infrastructure chief describes it (reported, one speaker) Sequoia
3.2 GW
Load the Texas grid can lose at once before causing serious issues under some conditions, as the essay author reports Ryan McEntush
3.2 GW, 2028 to 2032
Power one planned campus contracted from its utility, delivered in phases, as the lab announced OpenAI
800 MW in 2028
First capacity of a planned 8 gigawatt-IT campus, expected on existing utility infrastructure, as the lab announced OpenAI
  • An AI data center is concrete, an enclosure, electrical yards, mechanical yards and cooling, with row after row of power distribution, a great deal of network and some storage. Sequoia
  • The building is planned for 25 to 30 years while the hardware in it lasts about 6, so an AI hall is more purpose-built and co-designed with the racks, even to cooling and power distribution. Sequoia
  • Cooling has moved from air to liquid: any state-of-the-art data center is already on liquid cooling. a16z

When it breaksA fault pulled a whole load off the grid. Many data centers switch to backup power at the first voltage dip to protect hardware, so one bad fault can pull an enormous load off the grid in seconds. It happened earlier this year in Virginia and was handled well. Ryan McEntush